Boeing posts loss as 787 jet deliveries stall with ‘no firm end in



© Reuters. FILE PHOTO: A Boeing 777X airplane taxis during an attempted first test flight from the company’s plant in Everett, Washington, U.S. January 24, 2020. REUTERS/Lindsey Wasson/File Photo

By Uday Sampath Kumar and Eric M. Johnson

(Reuters) -Boeing Co said on Wednesday it incurred $4.5 billion charges in the fourth quarter on its sidelined 787 program, obscuring the U.S. planemaker’s long-awaited return to positive cash flow fueled by rebounding 737 MAX deliveries.

The planemaker sank to a loss after two quarters of profits because of the charges. Shares in Boeing (NYSE:) fell 3.6% as the array of charges and uncertainty over the 787 program dwarfed a surprise return to positive free cash flow and plans to increase production on the 737 and 777.

The quarterly results underscore the challenges Boeing faces as it seeks to rebound from the coronavirus pandemic and 737 MAX safety crises, while navigating industrial and regulatory currents on its bigger 787 and 777X flagship.

Its ability to resume deliveries to airlines depends on approvals from the U.S. Federal Aviation Administration.

“Here we go again. Just as we saw with the 737 MAX, Boeing is now racking up massive charges on the 787 with no firm end in sight, and its fate in the hands of the FAA,” said Vertical Research Partners analyst Rob Stallard.

Reuters reported last week that deliveries of the 787 are expected to remain frozen for months as U.S. regulators review repairs and inspections over structural flaws in the jets, while designs for the larger 777X face further regulatory pushback from Europe.

“While we never want to disappoint our customers or miss expectations, the work we’re putting in now will build stability and predictability going forward,” Boeing Chief Executive Dave Calhoun told employees in a memo seen by Reuters.

Calhoun stopped short of saying when deliveries of 787 would resume. The program remains at a low production rate, with an expected gradual return to five per month over time, Boeing said. Calhoun and Chief Financial Officer Brian West later told investors on a call 737 MAX deliveries and service would resume in China’s crucial aviation market in the first quarter.

Boeing unveiled a $3.5 billion pre-tax non-cash charge related to 787 delivery delays and customer concessions, and another $1 billion in abnormal production costs.

Boeing had previously forecast low production rates and rework for the 787 due to manufacturing flaws and required inspections and repairs to result in about $1 billion of abnormal costs – putting the overall price tag at some $5.5 billion.

HAIR-THIN GAPS

At its U.S. factories, Boeing is combing through parked 787s with ultrasound devices and tools to measure gaps barely visible to the naked eye. The gaps – left in the process for making carbon-composite structures that make the jet lighter and cheaper to fly – are the width of a human hair but violate Boeing’s specifications.

The company reported a core operating loss…